Sunday, July 18, 2010

Gautrain Takes Taxis Business

Johannesburg's new regional rail system Guatrain has usurped much of the business of metered taxis and minibuses traveling the route between OR Tambo International Airport and Sandton.

With their hopes of making a killing during the World Cup dashed, meter-taxi drivers now face the reality that the Gautrain has fundamentally changed travel for good on this route.

The Gautrain has transported 400 000 people since it launched last month, some of whom just wanted to experience this mode of transport.

Meter taxis charge up to R500 for a single trip on this route, while the journey costs R100 on the Gautrain.

Gautrain pushes taxis off profit track
Fin 24
July 18, 2010

Thursday, April 22, 2010

Gautrain Leg Nearly Complete

Construction is nearly complete on the first leg of the new Gautrain regional rail link connecting metro Johannesburg with OR Tambo International Airport.

Trackworks and associated railway infrastructure are complete and this section of the Gautrain route is now operational. Ticket vending machines and fare gates have been installed and testing of the system is in progress.

At Sandton station, construction work on the multi-level parkade and erection of structural steelwork canopies that will form the entrance structure on the corner of Rivonia Road and West Street is under way.

Tracks almost clear for Gautrain
Pretoria News
April 21, 2010

Tuesday, April 20, 2010

Zuma Says Transportation System Ready For GDP-Boosting World Cup

With the opening of the new central terminal building at OR Tambo International Airport in Johannesburg, South African President Jacob Zuma said Tuesday that the country's transportation infrastructure was ready for the World Cup and its transportation demands. He also said that theWorld Cup would add about 4.9 billion Rand (~$662.7 million USD) to the country's gross domestic product in 2010.

He said that as the airport's name changed from the Johannesburg International Airport to the OR Tambo International Airport in 2006, "so did its form and size".

A transport action plan was developed in 2005 in preparation for the World Cup, as part of which R20bn was put into expanding airports countrywide.

"... Now we are seeing the results," said Zuma.

SA ready for World Cup - Zuma
News24
April 20, 2010

Tuesday, March 23, 2010

Traffic Not a Problem During Cup: Gauteng Premier

Infrastructure improvements should be finishing up in Gauteng province, leading its premier to announce that traffic will not be a problem during the World Cup.

"We are confident that in the next few months, traffic on our roads will flow without the congestion and the inconvenience that is currently being encountered," [Premier Nomvula Mokonyane] said in her speech to the Foreign Correspondents' Association.

"We have been given a guarantee by the South African National Roads Agency (SANRAL) that key parts of the Gauteng Freeway Improvement Project will be completed by end of April 2010."

The R21 highway joining the OR Tambo International Airport and the cities of Johannesburg and Tshwane would be completed by the end of April, with three lanes opened in both directions, she assured the foreign media.

Traffic to ease during World Cup - Mokonyane
Independent Online
March 23, 2010

Sunday, February 14, 2010

Rail Link From Johannesburg Airport to Be Ready in Time for World Cup

A rapid rail link between Johannesburg's Sandton Station and the city's OR Tambo International Airport will be ready in time for the World Cup, according to officials at Gautrain.

Although the train is not a World Cup project, its readiness would ease concern that existing public transport plans may not be sufficient for the many thousands of visitors expected in SA for the event.

Barbara Jensen, spokeswoman for the project, told Business Day yesterday that although the airport-to-Sandton link was not a World Cup project, "chances are very good that it can be ready".

She said the project managers would make a final call on the deadline within the next two weeks.

South Africa: Gautrain Says Airport Line May Be Ready for World Cup
Business Day
February 11, 2010

Sunday, February 7, 2010

Police Chief OKs Johannesburg Airport

South Africa's police minister has deemed the upgraded OR Tambo International Airport in Johannesburg ready and safe to welcome teams and tourists during the World CUp.

"We are satisfied with the progress made at the airport and I am confident that the world cup will be safe. Our law enforcement agencies are ready for the 2010 FIFA World Cup," he said.

Mthethwa was visiting the country's largest port of entry on Tuesday as part of his ongoing campaign to check the state of readiness of all ports of entry, including airports and borders before the mega tournament.

South Africa: Or Tambo Ready to Welcome 2010 Guests
BuaNews
January 26, 2010

Saturday, November 14, 2009

Gautrain Operation Set to Begin Late

The Gautrain regional train system will not be operational until half-way through the World Cup tournament, according to Gautrain officials. The regional system had planned to have the first leg of its system operational between Johannesburg, Pretoria, and OR Tambo International Airport in time for the 2010 World Cup, beginning in June.

Organisers of South Africa 2010 had hoped fans would arrive at Johannesburg airport and board a high-speed train to the commercial centre.

Instead, most football fans' first experience will now be a taxi or a shuttle bus and more than likely a sizable traffic jam, our correspondent says.

For the past three years builders have been working on the Gautrain - an ambitious $3.5bn (£2bn) project linking Johannesburg, Pretoria and the airport.

Contractors, under pressure to complete before next June's deadline, demanded an additional $180m (£107m) to accelerate their work and hit the target.

SA World Cup rail project delayed
BBC
November 9, 2009

Wednesday, July 8, 2009

Gautrain 65% Complete, According to Officials

The development of the Gautrain regional rail system is about 65% complete, according to train officials. One segment had been planned for completion by the 2010 World Cup, but it is now unclear whether that portion will be complete in time.

[Gautrain Management Authority chief executive officer Jack] Van der Merwe said that 14km of the 15km of tunnelling has been completed and that 25 percent of the track-laying has been done.

The bulk of the civil works has been completed.

Van der Merwe said an announcement would be made next month on whether the OR Tambo to Sandton route would be complete two weeks before the 2010 Fifa World Cup.

Gautrain construction is 65% done - managers
Independent Online
July 2, 2009

Thursday, June 4, 2009

Gautrain Project '60% Complete'

The rapid rail link connecting Johannesburg's OR Tambo International Airport and the rest of the region is apparently 60% complete, according to officials. The phase expected to be complete next June may be accelerated to meet demand during the 2010 World Cup, which will begin in early June 2010. The entire project won't be complete until around 2011.

The first phase is still scheduled to be up and running by the end of June next year, although it may be accelerated to wrap in May, in time for the 2010 FIFA World Cup. The decision on this is still pending.

The initial phase encompasses the rail network between the OR Tambo International Airport and Sandton, and includes the stations at OR Tambo, Rhodesfield, Marlboro and Sandton, together with the depot and operations control centre located near Allandale road, in Midrand.

The second phase, being constructed concurrently, will be completed in 54 months, towards 2011.

Source:
Gautrain project 60% completed
Engineering News
May 29, 2009