Friday, May 14, 2010

First Phase of Gautrain Ready Before Cup

The first leg of Gauteng Province's Gautrain will be up and running by June 8, according to transit officials.

French construction giant Bouygues said the train's first segment, linking OR Tambo International Airport and the posh Johannesburg suburb of Sandton, will open in time for the June 11 kick-off of Africa's first World Cup.

The segment "will be handed over on June 8, three weeks ahead of our original schedule," said Christian Gazaignes, Bouygues' executive director.

Africa's first high-speed train to open ahead of World Cup
Agence France Presse
May 7, 2010

Thursday, April 22, 2010

Gautrain Leg Nearly Complete

Construction is nearly complete on the first leg of the new Gautrain regional rail link connecting metro Johannesburg with OR Tambo International Airport.

Trackworks and associated railway infrastructure are complete and this section of the Gautrain route is now operational. Ticket vending machines and fare gates have been installed and testing of the system is in progress.

At Sandton station, construction work on the multi-level parkade and erection of structural steelwork canopies that will form the entrance structure on the corner of Rivonia Road and West Street is under way.

Tracks almost clear for Gautrain
Pretoria News
April 21, 2010

Sunday, February 14, 2010

Rail Link From Johannesburg Airport to Be Ready in Time for World Cup

A rapid rail link between Johannesburg's Sandton Station and the city's OR Tambo International Airport will be ready in time for the World Cup, according to officials at Gautrain.

Although the train is not a World Cup project, its readiness would ease concern that existing public transport plans may not be sufficient for the many thousands of visitors expected in SA for the event.

Barbara Jensen, spokeswoman for the project, told Business Day yesterday that although the airport-to-Sandton link was not a World Cup project, "chances are very good that it can be ready".

She said the project managers would make a final call on the deadline within the next two weeks.

South Africa: Gautrain Says Airport Line May Be Ready for World Cup
Business Day
February 11, 2010

Wednesday, October 21, 2009

Gautrain Tunneling Pushes Project Forward

Progress on the Gautrain regional rail project near Johannesburg is moving ahead, as a critical tunnel nears completion.

[W]ith just one press of the button the blast would take down the hewn wall and open up the 15,5km tunnel between Park station and Sandton, making one continuous conduit that has taken three years to construct.

The tunnels came from opposite directions - one was en route from the Shaft E2 site in Rosebank, while the other came from the Park station site.

Gautrain tunnel becomes one
The Star
October 14, 2009

Wednesday, July 8, 2009

Gautrain 65% Complete, According to Officials

The development of the Gautrain regional rail system is about 65% complete, according to train officials. One segment had been planned for completion by the 2010 World Cup, but it is now unclear whether that portion will be complete in time.

[Gautrain Management Authority chief executive officer Jack] Van der Merwe said that 14km of the 15km of tunnelling has been completed and that 25 percent of the track-laying has been done.

The bulk of the civil works has been completed.

Van der Merwe said an announcement would be made next month on whether the OR Tambo to Sandton route would be complete two weeks before the 2010 Fifa World Cup.

Gautrain construction is 65% done - managers
Independent Online
July 2, 2009

Thursday, June 4, 2009

Gautrain Project '60% Complete'

The rapid rail link connecting Johannesburg's OR Tambo International Airport and the rest of the region is apparently 60% complete, according to officials. The phase expected to be complete next June may be accelerated to meet demand during the 2010 World Cup, which will begin in early June 2010. The entire project won't be complete until around 2011.

The first phase is still scheduled to be up and running by the end of June next year, although it may be accelerated to wrap in May, in time for the 2010 FIFA World Cup. The decision on this is still pending.

The initial phase encompasses the rail network between the OR Tambo International Airport and Sandton, and includes the stations at OR Tambo, Rhodesfield, Marlboro and Sandton, together with the depot and operations control centre located near Allandale road, in Midrand.

The second phase, being constructed concurrently, will be completed in 54 months, towards 2011.

Source:
Gautrain project 60% completed
Engineering News
May 29, 2009